(BID) Resurfacing of Various County Roads - Batch 3
Last updated by Addendum #1 on May 15, 2025 1:26 PMSee what changed
SPLOST
74521, 75091, 91276, 91395, 91396... show all
Project ID: 25-70
Release Date: Wednesday, April 23, 2025
· Due Date: Wednesday, May 21, 2025 3:00pm
Posted Wednesday, April 23, 2025 10:00am
All dates & times in Eastern Time
Question & Answer
Questions and clarifications about the project
1. ESTIMATED BUDGET Apr 25 2025 at 2:02 PM
- Anonymous Apr 25 2025 at 2:02 PMUser information is private
What is the estimated construction budget for this project? - May 15 2025 at 8:56 AMHenry County
A construction budget has not been determined for this project.
2. Work/Lane Closure Hours May 5 2025 at 7:29 PM
- Anonymous May 5 2025 at 7:29 PMUser information is private
What will be the allowed work/lane closure hours for this project? - May 15 2025 at 8:56 AMHenry County
No night will be allowed in residential areas between the hours of 8 pm and 6am. Work restrictions may be implemented, at the discretion of the Henry County, if conditions arise that cause significant congestion and extensively restricts work and school traffic. Contingent upon the individual roads' traffic volumes, proximity to schools, and at the discretion of Henry County, work restrictions can be be implemented as follows: No work shall impede traffic between the hours of 6 am and 9 am No work shall impede traffic between the hours of 3 pm to 6 pm.
3. Road Limits May 5 2025 at 7:29 PM
- Anonymous May 5 2025 at 7:29 PMUser information is private
Would Henry Co. provide all bidding contractors the begin and end of each road that is in this project? - May 15 2025 at 8:56 AMHenry County
This will be provided on an attachment for the addendum.
4. Toccoa Court May 5 2025 at 7:30 PM
- Anonymous May 5 2025 at 7:30 PMUser information is private
What is the location of Toccoa Ct.? - May 15 2025 at 8:56 AMHenry County
The name of the road is Toccoa Place, located in Falling Waters Subdivision.
5. Road Length & Widths May 5 2025 at 7:31 PM
- Anonymous May 5 2025 at 7:31 PMUser information is private
Would Henry Co. provide all bidding contractors the length and width of each road? - May 15 2025 at 8:56 AMHenry County
This will be provided on an attachment for the addendum.
6. Width for Shoulder Grading May 5 2025 at 7:31 PM
- Anonymous May 5 2025 at 7:31 PMUser information is private
What will be the required width of the shoulder building? - May 15 2025 at 8:56 AMHenry County
The shoulder building will required to cover the width of the entire disturbed grass area, or a width of 4 feet, whichever one is lesser.
7. Location for Type C Silt Fence May 5 2025 at 7:32 PM
- Anonymous May 5 2025 at 7:32 PMUser information is private
Can Henry Co. identify the location of the Type C Silt Fence? - May 15 2025 at 8:56 AMHenry County
The item for Type C silt fence is incidental. It will be required at the direction of Henry County in the event that an environmentally sensitive area is impacted.
8. Patching Locations May 5 2025 at 7:33 PM
- Anonymous May 5 2025 at 7:33 PMUser information is private
It is assumed that Hayes Circle, Hayes Ct. & Hayes Ln will receive the Patching – is this correct? - May 15 2025 at 8:56 AMHenry County
These three roads require variable depth milling and 2 inches of 12.5 mm topping.
9. Tons for Patching Per Road May 5 2025 at 7:34 PM
- Anonymous May 5 2025 at 7:34 PMUser information is private
What will be the estimated tons of Patching on each road? - May 15 2025 at 8:56 AMHenry County
The patching item is incidental and usage is contingent upon the actual field conditions once operations commence. Please see Contract Supplemental Provision G.II.R.
10. Patching Widths May 5 2025 at 7:34 PM
- Anonymous May 5 2025 at 7:34 PMUser information is private
Will the patch areas be marked 7’ or wider so a milling machine can be used to remove the marked areas? - May 15 2025 at 8:56 AMHenry County
Yes.
11. Asphalt Mix for Patching May 5 2025 at 7:35 PM
- Anonymous May 5 2025 at 7:35 PMUser information is private
It looks like Patching asphalt mix should be 12.5mm – is this correct? - May 15 2025 at 8:56 AMHenry County
No. Patching shall be placed with either 25 MM or 19 MM asphalt.
12. Depth for Patching May 5 2025 at 7:35 PM
- Anonymous May 5 2025 at 7:35 PMUser information is private
It looks like the depth of the Patching will be 2” – is this correct? - May 15 2025 at 8:56 AMHenry County
Please see Contract Supplemental Provision G.II.R. It shall be two inches unless otherwise specified by Henry County.
13. Wet Cure for FDR May 5 2025 at 7:36 PM
- Anonymous May 5 2025 at 7:36 PMUser information is private
Would Henry Co. consider wet curing the FDR instead of Prime & Sanding? - May 15 2025 at 8:56 AMHenry County
Wet curing may be accepted in lieu of prime and sanding for subdivisions. Prime and sand will be required for roads outside of subdivisions.
14. Rumble Strips May 5 2025 at 7:37 PM
- Anonymous May 5 2025 at 7:37 PMUser information is private
Will the Rumble Strips be thermoplastic or asphalt? - May 15 2025 at 8:56 AMHenry County
The item for the rumble strips shall be removed from the contract.
15. Roads for Rumble Strips May 5 2025 at 7:37 PM
- Anonymous May 5 2025 at 7:37 PMUser information is private
Which road(s) will get the Rumble Strips? - May 15 2025 at 8:56 AMHenry County
The item for the rumble strips shall be removed from the contract.
16. Variable Depth Milling - Roads May 5 2025 at 7:38 PM
- Anonymous May 5 2025 at 7:38 PMUser information is private
Is the 30,000 sy of Variable Depth Milling on Hayes Circle, Hayes Ct. & Hayes Ln. only? - May 15 2025 at 8:56 AMHenry County
Yes.
17. Cover Milled Surfaces May 5 2025 at 7:39 PM
- Anonymous May 5 2025 at 7:39 PMUser information is private
How long can the milled surface remain without asphalt final surface paving? - May 15 2025 at 8:56 AMHenry County
7 days is the maximum time allowed.
18. Mill for Side Roads May 5 2025 at 7:39 PM
- Anonymous May 5 2025 at 7:39 PMUser information is private
Will the contractor be required to mill into all side roads for the final 12.5mm asphalt topping? - May 15 2025 at 8:56 AMHenry County
In most cases, milling into the side roads to a distance of approximately 30 feet will be required for a smooth transition.
19. Mill and Pave into Driveways May 5 2025 at 7:40 PM
- Anonymous May 5 2025 at 7:40 PMUser information is private
Will the contractor be required to mill and pave into any driveways? - May 15 2025 at 8:56 AMHenry County
This will be contingent upon the existing condition of the driveways. Most existing driveways can be overlayed or milled and overlayed for a smooth transition.
20. Speed Table Spec/Details May 5 2025 at 7:41 PM
- Anonymous May 5 2025 at 7:41 PMUser information is private
Can you provide a Specification and or Construction Detail for the Asphalt Speed Tables? - May 15 2025 at 8:56 AMHenry County
There is no GDOT specification or detail for the speed tables. They are only placed at the direction of Henry County and when warranted by special circumstances. They can be formed manually by various methods and constructed with the intent of slowing traffic.
21. Speed Table Locations May 5 2025 at 7:42 PM
- Anonymous May 5 2025 at 7:42 PMUser information is private
Which road(s) will the Asphalt Speed Tables be installed on? - May 15 2025 at 8:56 AMHenry County
The asphalt speed tables were added to the contract as incidental items; they will only be installed at the direction of Henry County.
22. GAB Locations May 5 2025 at 7:43 PM
- Anonymous May 5 2025 at 7:43 PMUser information is private
Which roads will the 100 tons of GAB be placed on? - May 15 2025 at 8:56 AMHenry County
The GAB has been added as an incidental item in the event that it is required for temporary usage to make a road more passable or for temporary driveway access.
23. GAB Scope May 5 2025 at 7:44 PM
- Anonymous May 5 2025 at 7:44 PMUser information is private
What is the intended scope for the GAB? A detail or narrative explanation will be helpful for the best price. - May 15 2025 at 8:56 AMHenry County
Please see response to question # 22.
24. Message Boards May 5 2025 at 7:44 PM
- Anonymous May 5 2025 at 7:44 PMUser information is private
How many Message Boards will be required on this project? - May 15 2025 at 8:56 AMHenry County
Two message boards will be required for mainline roads (one in each direction), and they will need to be placed 7 days prior to commencement of work for advanced warning.
25. Reclaim Curb Gutters for Mill and Paving May 5 2025 at 7:45 PM
- Anonymous May 5 2025 at 7:45 PMUser information is private
On roads with curb and gutter should the finished asphalt be flush with the lip of the gutter? - May 15 2025 at 8:56 AMHenry County
Yes.
26. Advanced Warning Signs May 5 2025 at 7:46 PM
- Anonymous May 5 2025 at 7:46 PMUser information is private
Will the contractor be required to post mount the advanced warning signs or can the advanced warnings signs be placed on tripod stands? - May 15 2025 at 8:56 AMHenry County
Post mounted signs will be required for advanced warning on all mainline roads. For the remaining roads, tripod mounted signage will suffice.
27. QC Testing May 5 2025 at 7:47 PM
- Anonymous May 5 2025 at 7:47 PMUser information is private
Will the contractor be required to hire and pay a 3rd party firm to perform any asphalt compaction test and or quality control testing on this project? - May 15 2025 at 8:56 AMHenry County
No. A private consultant will be selected by Henry County to perform this work.
28. DBE May 6 2025 at 5:34 PM
- Anonymous May 6 2025 at 5:34 PMUser information is private
Can the Contractor use SVDBE Subs to meet the DBE Goal? If SVDBE's are allowed, what percentage of the overall goal can they be used for? - May 15 2025 at 8:56 AMHenry County
Yes, the goal can be met by prime contracting, sub-contracting, joint-venture or mentor/protégé relationship.
29. FDR Testing May 6 2025 at 5:35 PM
- Anonymous May 6 2025 at 5:35 PMUser information is private
Is the County responsible for supplying the FDR testing? - May 15 2025 at 8:56 AMHenry County
Please see response to question # 27.
30. FDR Mix Design May 6 2025 at 5:36 PM
- Anonymous May 6 2025 at 5:36 PMUser information is private
Is the County responsible for supplying the FDR Mix Designs? - May 15 2025 at 8:56 AMHenry County
Please see response to question # 27.
31. Grading for Shoulders May 6 2025 at 5:36 PM
- Anonymous May 6 2025 at 5:36 PMUser information is private
Which streets will require the shoulder grading? - May 15 2025 at 8:56 AMHenry County
All roads that require FDR that do not have existing curb and gutter will require shoulder grading.
32. Section 301 & 315 Specs May 6 2025 at 5:38 PM
- Anonymous May 6 2025 at 5:38 PMUser information is private
It appears that the version of section 301 and 315 in the bid documents wants the contractor to apply a single 89 surface treatment layer or OGI as the curing method on roads that are greater than or equal to 400 ADT. Doing this instead of just using prime coat and sand will dramatically increase costs for this project and extend the completion for the project. Can the County please allow the contractor to use prime coat and sand on all FDR streets as the curing method? - May 15 2025 at 8:56 AMHenry County
For this contract, prime and sand will be accepted for all FDR roads.
33. ADT on FDR Streets May 6 2025 at 5:39 PM
- Anonymous May 6 2025 at 5:39 PMUser information is private
Can the County please provide the ADT on all FDR streets as this relates to the current type of curing method required per section 301 and 315 in the bid documents? - May 15 2025 at 8:56 AMHenry County
Prime and Sand will be acceptable for all projects in this contract with no consideration for the ADT.
34. Completion Time May 6 2025 at 5:39 PM
- Anonymous May 6 2025 at 5:39 PMUser information is private
Given the size of this project, can the County please extend the completion time to 540 calendar days? - May 15 2025 at 8:56 AMHenry County
Yes. It shall be noted that there will be no asphalt index or fuel adjustments for this project.
35. Spread Rate for FDR May 6 2025 at 5:40 PM
- Anonymous May 6 2025 at 5:40 PMUser information is private
What is the intended spread rate (#/SY) for the cement in the FDR? - May 15 2025 at 8:56 AMHenry County
This will be determined by a mix design established by a consultant contracted by Henry County. Typically, subdivision roads require approximately 35 lbs per square yard and most mainline roads require approximately 55 lbs per square yard.
36. Wet Cure May 7 2025 at 1:36 PM
- Anonymous May 7 2025 at 1:36 PMUser information is private
If wet curing for the FDR is allowed, which streets will this be allowed on? - May 15 2025 at 8:56 AMHenry County
Wet curing will be allowed for subdivision roads.
37. Prime Coat Quantity May 7 2025 at 1:39 PM
- Anonymous May 7 2025 at 1:39 PMUser information is private
The Prime Coat Quantity appears to be overstated as there is enough quantity for more than every road. Can the County please adjust this quantity for only the roads that will require the Prime Coat? Assuming wet curing is allowed on the smaller roads. - May 15 2025 at 8:56 AMHenry County
Wet curing will be allowed for subdivision roads. The quantity will remain the same in the event that we need to utilize the maximum spread application for the other roads.