Question & Answer
Questions and clarifications about the project
1. ESTIMATED BUDGET Apr 21 2025 at 1:39 PM
- Anonymous Apr 21 2025 at 1:39 PMUser information is private
What is the estimated construction budget for this project? - May 7 2025 at 10:16 AMHenry County
The construction budget for this project has not been determined.
2. Road Map or Beg/End for Roads Apr 28 2025 at 7:25 PM
- Anonymous Apr 28 2025 at 7:25 PMUser information is private
Can you please provide either a location map for each of the roads or begin and end points for each of the roads to make sure we have roads mapped correctly? - May 7 2025 at 10:16 AMHenry County
The roads in this contract are to resurfaced from beginning to end, unless otherwise designated start and end points are designated on the attachment provided in Addendum #1.
3. Work/Lane Closure Restrictions Apr 28 2025 at 7:26 PM
- Anonymous Apr 28 2025 at 7:26 PMUser information is private
Can you please provide the allowable Work/Lane Closure hours that will be used for this project? - May 7 2025 at 10:16 AMHenry County
No night will be allowed in residential areas between the hours of 8 pm and 6am. Work restrictions may be implemented, at the discretion of the Henry County, if conditions arise that cause significant congestion and extensively restricts work and school traffic. Contingent upon the individual roads' traffic volumes, proximity to schools, and at the discretion of Henry County, work restrictions can be be implemented as follows: No work shall impede traffic between the hours of 6 am and 9 am No work shall impede traffic between the hours of 3 pm to 6 pm.
4. Road Details Apr 28 2025 at 7:28 PM
- Anonymous Apr 28 2025 at 7:28 PMUser information is private
Could you please provide the road lengths, widths and scope details for each of the roads? This information help to get Henry Co the best prices. - May 7 2025 at 10:16 AMHenry County
An attachment will be provided, in Addendum #1, with road lengths and widths. The scope details for each road are listed in the contract documents.
5. FDR Limits for Each Road Apr 28 2025 at 7:28 PM
- Anonymous Apr 28 2025 at 7:28 PMUser information is private
Will the limits of the FDR Scope be limited to the travel lanes only? Excluding outside turn lanes and side roads? - May 7 2025 at 10:16 AMHenry County
FDR will be designated only for travel lanes. Typically, turn lanes can be milled and overlayed with the exception of turn lanes that have extremely poor existing conditions. For turn lanes that are in poor condition, Henry County will have the discretion to use FDR.
6. Patching New Hope Rd Apr 28 2025 at 7:30 PM
- Anonymous Apr 28 2025 at 7:30 PMUser information is private
When we were out on New Hope Road we were unable to find the bridge, so we are not sure where the patching will be done. Can you provide better details for the Patching on New Hope Road? - May 7 2025 at 10:16 AMHenry County
The correct name of the road referenced here is Leguin Mill Road. The road changes names from New Hope to Leguin Mill just north of Tussahaw Creek.
7. Mill & Pave Into Side Rds Apr 28 2025 at 7:32 PM
- Anonymous Apr 28 2025 at 7:32 PMUser information is private
Can you please confirm that your intent is to Mill and Pave into the adjacent Side Roads? If so, please define how far back into the Side Road you want to go to. - May 7 2025 at 10:16 AMHenry County
Correct. We typically mill and pave approximately 30 feet into side roads.
8. Mill Cover Up Apr 28 2025 at 7:34 PM
- Anonymous Apr 28 2025 at 7:34 PMUser information is private
Can you please define how long a Milled Surface can remain uncovered before the final surfaces are placed? Typically, 7 days has been a reasonable duration. - May 7 2025 at 10:16 AMHenry County
7 days is the maximum allowed days for milled surfaces to be exposed.
9. Grading for Shoulders Apr 28 2025 at 7:34 PM
- Anonymous Apr 28 2025 at 7:34 PMUser information is private
Can you please confirm that the Grading Per Mile quantity is for Centerline Miles? - May 7 2025 at 10:16 AMHenry County
Centerline
10. Grading for Shoulders Apr 28 2025 at 7:35 PM
- Anonymous Apr 28 2025 at 7:35 PMUser information is private
Can you please identify which of the roads will required Grading Per Mile? - May 7 2025 at 10:16 AMHenry County
All roads that require FDR that do not have existing curb and gutter will require shoulder grading.
11. Locust Road and Rocky Creek Road Apr 30 2025 at 9:55 AM
- Anonymous Apr 30 2025 at 9:55 AMUser information is private
Can the County provide the begin and end points for Locust Road and Rocky Creek Road? - May 7 2025 at 10:16 AMHenry County
Locust Road (from SR 42 to end of pavement near 1118 Locust Road) Rocky Creek Road (from South Hampton Road to County Line)
12. New Hope Road and Old Jackson Road Apr 30 2025 at 9:56 AM
- Anonymous Apr 30 2025 at 9:56 AMUser information is private
We are having a hard time figuring out the exact location for where the patching and overlay on New Hope Road and Old Jackson Road. Can the County please provide a more accurate location? - May 7 2025 at 10:16 AMHenry County
The section referenced as New Hope Road in the contract is actually Leguin Mill Road. The road name changes from New Hope Road to Leguin Mill Road just north of Tussahaw Creek. The section of Old Jackson that will require patching is located approximately 800 feet north of Coan Drive, over Tussahaw Creek.
13. 12.5mm Topping on New Hope Road and Old Jackson Road Apr 30 2025 at 9:57 AM
- Anonymous Apr 30 2025 at 9:57 AMUser information is private
Can the County provide the 12.5mm topping tons anticipated for New Hope Road and Old Jackson Road? - May 7 2025 at 10:16 AMHenry County
Approximately 200 tons per road
14. Cure Time for FDR Apr 30 2025 at 9:58 AM
- Anonymous Apr 30 2025 at 9:58 AMUser information is private
How many days will the FDR need to cure before the paving takes place? - May 7 2025 at 10:16 AMHenry County
The FDR will need attain 300 PSI prior to placement of asphalt. This typically takes 4 to 7 days.
15. DBE Apr 30 2025 at 10:01 AM
- Anonymous Apr 30 2025 at 10:01 AMUser information is private
Can the Contractor use SVDBE Subs to meet the DBE Goal? If SVDBE's are allowed, what percentage of the overall goal can they be used for? - May 7 2025 at 10:16 AMHenry County
Yes, the goal can be met by prime contracting, sub-contracting, joint-venture or mentor/protégé relationship.
16. FDR Testing Apr 30 2025 at 10:02 AM
- Anonymous Apr 30 2025 at 10:02 AMUser information is private
Is the County responsible for supplying the FDR testing? - May 7 2025 at 10:16 AMHenry County
Yes.
17. FDR Mix Design Apr 30 2025 at 10:03 AM
- Anonymous Apr 30 2025 at 10:03 AMUser information is private
Is the County responsible for supplying the FDR Mix Designs? - May 7 2025 at 10:16 AMHenry County
Yes.
18. Grading for Shoulders Apr 30 2025 at 10:04 AM
- Anonymous Apr 30 2025 at 10:04 AMUser information is private
Which streets will require the shoulder grading? - May 7 2025 at 10:16 AMHenry County
All roads that require FDR that do not have existing curb and gutter will require shoulder grading.
19. North Mount Carmel Road Apr 30 2025 at 10:05 AM
- Anonymous Apr 30 2025 at 10:05 AMUser information is private
Can the County please provide the begin and end point for North Mount Carmel Road? - May 7 2025 at 10:16 AMHenry County
The road to be resurfaced is South Mount Carmel (from SR 81 to Mt. Carmel Road)
20. Post Mounted Signs Apr 30 2025 at 10:06 AM
- Anonymous Apr 30 2025 at 10:06 AMUser information is private
Are post mounted signs required? - May 7 2025 at 10:16 AMHenry County
Post mounted signs will be required for advanced warning on all roads listed in G.II.A. and G.II.E. For the remaining roads, tripod mounted signage will suffice.
21. Section 315 CSRB Apr 30 2025 at 10:11 AM
- Anonymous Apr 30 2025 at 10:11 AMUser information is private
It appears that the version of section 315 in the bid documents wants the contractor to apply a single 89 surface treatment layer or OGI as the curing method on roads that are greater than or equal to 400 ADT. Doing this instead of just using prime coat and sand will dramatically increase costs for this project and extend the completion for the project. Can the County please allow the contractor to use prime coat and sand on all FDR streets as the curing method? - May 7 2025 at 10:16 AMHenry County
For this contract, prime and sand will be accepted for all FDR roads.
22. ADT on FDR Streets Apr 30 2025 at 10:12 AM
- Anonymous Apr 30 2025 at 10:12 AMUser information is private
Can the County please provide the ADT on all FDR streets as this relates to the type of curing method required per section 315 in the bid documents? - May 7 2025 at 10:16 AMHenry County
Prime and sand will be a suitable curing method for the scope of this project. No ADT will be provided.
23. Prime Coat Quantity Apr 30 2025 at 10:14 AM
- Anonymous Apr 30 2025 at 10:14 AMUser information is private
If the intent is to prime and sand all FDR streets, then it appears the bid quantity is understated on the bid form. Can the County please adjust this quantity? - May 7 2025 at 10:16 AMHenry County
Prime and sand will not be required for subdivision roads.
24. Completion Time Apr 30 2025 at 10:16 AM
- Anonymous Apr 30 2025 at 10:16 AMUser information is private
Can the County please extend the completion time to 540 calendar days for this project? - May 7 2025 at 10:16 AMHenry County
Yes. It shall be noted that there will be no asphalt index or fuel adjustments for this project.
25. Spread Rate for FDR Apr 30 2025 at 10:18 AM
- Anonymous Apr 30 2025 at 10:18 AMUser information is private
What is the intended spread rate (#/SY) for the cement in the FDR? - May 7 2025 at 10:16 AMHenry County
This will be determined by a mix design established by a consultant contracted by Henry County. Typically, subdivision roads require approximately 35 lbs per square yard and most mainline roads require approximately 55 lbs per square yard.
26. Utilities Adjustments Apr 30 2025 at 2:40 PM
- Anonymous Apr 30 2025 at 2:40 PMUser information is private
Will Henry County Water Authority lower, raise, and adjust to grade any manholes and/or water valves in conflict with FDR? If not, will a pay item be added? - May 7 2025 at 10:16 AMHenry County
Henry County will coordinate with Henry County Water Authority to adjust manholes and or water valves as required for the scope of this work.
27. Milling for FDR Apr 30 2025 at 2:40 PM
- Anonymous Apr 30 2025 at 2:40 PMUser information is private
Will milling for FDR be paid for separately or is it considered incidental to FDR? - May 7 2025 at 10:16 AMHenry County
Milling (pulverizing the existing road) shall be incorporated in the overall cost for Cement Stabilized base. There will be no separate pay item for this work.
28. Shoulder Grading Apr 30 2025 at 2:40 PM
- Anonymous Apr 30 2025 at 2:40 PMUser information is private
Will Grading Adjust shoulder to Grade be paid by the Center Line Mile or Shoulder Mile? - May 7 2025 at 10:16 AMHenry County
Center Line
29. Pregrinding - FDR Apr 30 2025 at 2:41 PM
- Anonymous Apr 30 2025 at 2:41 PMUser information is private
Is the intent to pre-grind all existing pavement prior to FDR? - May 7 2025 at 10:16 AMHenry County
All methods shall comply with the GDOT Special Provision 301.3.05 Specifications as outlined in the Contract will be acceptable.
30. DBE Goal Apr 30 2025 at 2:41 PM
- Anonymous Apr 30 2025 at 2:41 PMUser information is private
Will the low bidder be required to meet the DBE benchmark of 11% in order to be awarded the contract? - May 7 2025 at 10:16 AMHenry County
If the low bidder cannot meet the DBE benchmark, the Bidder will be required to submit evidence demonstrating that "good faith efforts" were made to meet the goal. Please refer to pages 14, 17, and 77 of the solicitation.
31. Road Widening Apr 30 2025 at 2:41 PM
- Anonymous Apr 30 2025 at 2:41 PMUser information is private
Is the intent to widen any FDR roads or will they be paved back to their current width? - May 7 2025 at 10:16 AMHenry County
The intent is fort he FDR roads will be paved back to their existing widths. Henry County may elect to pave some roads slightly wider if conditions permit to allow for some area of paved shoulder.
32. Variable Message Boards Apr 30 2025 at 2:41 PM
- Anonymous Apr 30 2025 at 2:41 PMUser information is private
How many Variable Message Boards will be required for the roads under section A & E, and how long before construction should they be placed? - May 7 2025 at 10:16 AMHenry County
Two message boards will be required for these roads (one in each direction), and they will need to be placed 7 days prior to commencement of work for advanced warning.