Procurement Portal

Airfield Signage Rehabilitation
3. Construction Specifications
3.1. Project Description
The Airfield Signage Rehabilitation project at the New Smyrna Beach Municipal Airport generally consists of removal, installation, replacement, and rehabilitation of dilapidated airfield signage. The project also includes sign panel replacements for newer airfield signage and application of airfield pavement markings to coincide with the installation of new signage.
The project shall be completed on a working day basis and the Contractor shall be permitted procurement time for acquisition of materials ahead of the required field work. Working Days shall be charged to the contract time in accordance with the project specifications. Working days shall be charged only when on site performing the work detailed in the plans and specifications.
The project shall be completed in three separate work areas/phases to minimize impacts to the Airfield. The Contractor shall be escorted by the Owner at all times within the airport movement area, unless the Contractor completes airport mandated driver training and radio communications courses and is granted status as an approved "airfield escort." Proof of completion will be required.
3.2. Drawings
General:
The general character and scope of the work are illustrated by the drawings titled as follows:
22-22-AIR - Airfield Signage Rehabilitation
CITY OF NEW SMYRNA BEACH, FLORIDA
Checking of Drawings and Dimensions:
- The Contractor shall check all drawings and specifications immediately upon their receipt and shall promptly notify the Owner, in writing, of any discrepancies.
- The Contractor shall compare all drawings and verify the figures before layout out the work and shall be responsible for any errors, which might have been reasonably avoided thereby. When the type of equipment selected affects dimensions on the drawings, the Contractor shall adjust such dimensions as conditions may require to achieve the intent of the bid specifications.
Copies of Drawings and Specifications Furnished:
The Owner shall furnish to the Contractor and electronic file of drawings and specifications necessary for the execution of the work. One complete set of all drawings and specifications shall be maintained at the job site and shall be available to the Engineer at all times.
Drawings have been provided in Section 10, see Attachments
3.3. Specifications
See Attachments