Classroom Refresh at Willcox Elementary and Middle Schools
Last updated by Addendum #1 on Sep 20, 2024 9:25 PMSee what changed
Request For Qualification
Willcox Unified School District, #13
Project ID: 24-27-06
Release Date: Thursday, September 19, 2024
· Due Date: Wednesday, November 6, 2024 10:00am
Posted Thursday, September 19, 2024 3:53pm
All dates & times in Mountain Time - Arizona
Question & Answer
Questions and clarifications about the project
1. Pre-Submittal Metting Sep 27 2024 at 7:32 AM
- Anonymous Sep 27 2024 at 7:32 AMUser information is private
Where Is the location we will be meeting at today? The Contract Documents do not specify which location. Thank You, Jason - Sep 27 2024 at 9:14 AMArizona School Districts
We are meeting at the elementary school first
2. Unit Pricing Oct 2 2024 at 3:47 PM
- Anonymous Oct 2 2024 at 3:47 PMUser information is private
The Scope of work states that The Willcox Unified School District, #13 has an estimated budget of $1,050,000.00 for the entire project during the next 2 years and consists of 70 Classrooms. During the site visit it was stated that many of the classrooms have already received the renovations, but they were not sure how many in total. How many classrooms Have received renovations? What was the source of funding for these renovations? What was the price per classroom Budget compared to the final cost for the example classrooms we were shown during the walkthrough? - Oct 3 2024 at 12:53 PMArizona School Districts
Your submittal is about your qualifications, so many of questions are irrelevant. Funding source is Bond money. Cost is not a factor at this time.
3. GMP Oct 2 2024 at 3:48 PM
- Anonymous Oct 2 2024 at 3:48 PMUser information is private
During the walkthrough it was stated that only 3-4 classrooms will be worked on at a time and The final completion date is June 1, 2027. With Supply Chain disruptions, long lead times, Higher Inflation, and regular price increases becoming the new normal, it is very difficult to provide a GMP for 2.5 Years. We feel very confident that the entire project can easily be completed during one summer break in 2025, and with only one Contractor. Unless there is a delay in the available funding for this project, We see no reason why the project timeline should be stretched. Would you consider using 1 contractor for all remaining classrooms and allowing that contractor to set the final schedule for renovations to be completed, while guaranteeing no disruptions to regular school operations? - Oct 3 2024 at 12:53 PMArizona School Districts
Again your submittal is about your qualifications to get the work done. The District would consider one contractor. When thinking about a schedule remember these are occupied classrooms, not empty spaces.
4. acoustic tiles on wall Oct 3 2024 at 1:02 PM
- Anonymous Oct 3 2024 at 1:02 PMUser information is private
Has there been any testing on the acoustic tile under the wallpaper or the mastic? - Oct 21 2024 at 1:40 PMArizona School Districts
There is no need for testing since the project calls for drywall over the current wallpaper and mastic. The ceiling tiles are newer, so simply removing and replacing them is what is required.